Santa Rosa Junior College Campus Improvements

The project involved: construction of a six-level parking structure with a campus police substation at the ground level; road widening, median improvements, relocation of utilities, new signalization, and striping; as well as campus beautification, which included a new courtyard, walkways, lighting, wayfinding improvements, and landscaping.

Services Provided: The Allen Group provided project management services that included: managing all Requests for Information, submittals, contract modifications, and change orders; verifying and processing monthly progress payment requests; conducting weekly construction progress meetings; preparing weekly and monthly reports; coordinating inspection team activities; and project closeout.